Construction Methodology
- Stacked Bond CMU Masonry
- 12” Concrete Podium Deck with Hard Troweled Finish
- Type V Wood Framing
- Simpson Anchor Tie Down System
- Double 2” & 6” Demising Walls with 1” Off Set for Sound Mitigation
- Unit Flooring of Levelrock 3000 PSI with SRM Sound mat
- Diamond Grind and Lithium Polished Concrete unit Floors
- Four Stop Hydro Electric Elevator with Custom Powder Coated Cab
- Multi Stand Pipe NFPA 13 Fire Sprinkler System
- Urban Storm Water Mitigation
- Bio Filtration Planters Low Impact Water Distribution
- Single Gas Manifold
- Single Boiler Water heater with Recirculation System
- Cold Rolled Steel Loby Door with Off Set Dorma Hinge
- Sump Pump Water Filtration
- ERRCS Fire Annunciator Monitors
- FOB Access Controlled Security System
- Steel and wooden fabricated floating lobby ceiling system.
- Sliding and Overhead Secured Garage Gate Entry